Mong Duong 2 Achieves 10.5 Million Man-Hours With Total Progress Approximating 77%
Mong Duong 2 Achieves 10.5 Million Man-Hours With Total Progress Approximating 77%
Mong Duong 2 Achieves 10.5 Million Man-Hours With Total Progress Approximating 77%
We are proud to share that the Mong Duong 2 BOT Power Project continues to progress well with more than 5,000 people working on Site, total progress approximating 80% and construction progress 48%.
Mong Duong 2 BOT Power Project started construction during August 2011 and has achieved an overall progress to date of approximately 40%.
David Stone, Managing Director of the Company shared: “We are extremely happy to witness the commencement of lifting of the Unit 1 Steam Drum
It is our great pride to share that our Mong Duong Project has achieved the next significant safety milestone of 7 Million LTI Free man-hours.
Further to the milestone of 3 Million LTI Free man-hours achieved in August 2012, our company take great pride in sharing that our Mong Duong Project has achieved the next significant safety milestone of 4 Million LTI Free man-hours.