Haiyan Typhoon Relief
The aftermath of Haiyan Typhoon left many local public facilities such as the schools and markets partially damaged.
The aftermath of Haiyan Typhoon left many local public facilities such as the schools and markets partially damaged.
On 17 June 2014, we completed a significant milestone: synchronization of the gross 620MW First Unit of the Mong Duong II Project to the national 500 kV electrical grid.
On 17 June 2014, we completed a significant milestone: synchronization of the gross 620MW First Unit of the Mong Duong II Project to the national 500 kV electrical grid.
In addition to the daily job safety practices, we held many other activities on 28 May 2014 in celebration of the 2014 Safety Day. These activities, including onsite and offsite PPE inspection
The Second Unit is progressing well with the Boiler Hydro Test milestone recently completed.